Concept and Basic Engineering for Green Field Compression Hub Middle East
Confidential · 2024
The Concept & Basic Design package comprised a multidiscipline approach to determine the optimal hub configuration for the field. Lanza Engineers BV carried out the structural design for the following facilities:
Compression Platform
The 12,000 metric tonne compression topsides are to be installed by float over operation. Structural analyses performed include inplace, transport, and seismic sensitivity. The supporting jacket is installed by launch, with inplace analysis for skirt and through-pile jackets, transport analysis, seismic sensitivity, and boat impact.
Power Utility Platform
Topsides installed by float over operation, with inplace, transport, and seismic sensitivity analyses. The jacket is designed for installation by lifting or launch, covering inplace analysis for skirt and through-pile jackets, transport analysis, seismic sensitivity, and boat impact.
Bridges
The inter-platform bridges are installed by lifting operation. The scope covers inplace and lift analysis.